[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1168013":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1168013,830,2,"多选题","劳动力负荷曲线的原始条件包括（ ）项目总体施工统筹计划设备材料的交货方式、交货时间、供货状态等。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","施工项目的工程范围、工作规范、工程设计、施工图设计",true,{"key":16,"text":17,"correct":14},"B","施工项目所在地区的环境条件",{"key":19,"text":20,"correct":21},"C","项目部组织结构",false,{"key":23,"text":24,"correct":14},"D","项目的分部、分项工程量",{"key":26,"text":27,"correct":21},"E","项目保修期限","ABD","1.制订劳动力负荷曲线的原始条件:施工项目的工程范围、工作规范、工程设计、施工图设计；施工项目所在地区的环境条件：项目的分部、分项工程量；项目总体施工统筹计划；设备材料的交货方式、交货时间、供货状态等。",{"id":6,"name":31,"category":32,"favorite":33},"(劳务员)专业管理实务 岗位知识","建筑工程",0]