[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1168009":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1168009,830,2,"多选题","总承包企业的劳务主管部门应依据本公司生产部门的生产计划，制定劳动力招用、管理和储备的计划草案，汇总本公司各项目部计划需求后，按照（ ）提出解决途径。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","劳务队伍类型（工种）",true,{"key":16,"text":17,"correct":14},"B","需求时限",{"key":19,"text":20,"correct":14},"C","根据自有劳动力数量，进行劳动力平衡",{"key":22,"text":23,"correct":14},"D","确定缺口量",{"key":25,"text":26,"correct":27},"E","不需要考虑自有劳动力数量",false,"ABCD","总承包企业的劳务主管部门应依据本公司生产部门的年度、季度、月度生产计划，制定劳动力招用、管理和储备的计划草案。汇总本公司各项目部计划需求后，按照劳务队伍类型（工种）及需求时限，根据自有劳动力数量，进行劳动力平衡，确定缺口量，提出解决途径。",{"id":6,"name":31,"category":32,"favorite":33},"(劳务员)专业管理实务 岗位知识","建筑工程",0]