[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1168008":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1168008,830,2,"多选题","根据使用时间的不同，劳动力需求计划可分为（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","劳动力总需求计划",true,{"key":16,"text":17,"correct":18},"B","正常劳动力需求计划",false,{"key":20,"text":21,"correct":18},"C","特殊情况需求计划",{"key":23,"text":24,"correct":14},"D","年度劳动力需求计划",{"key":26,"text":27,"correct":14},"E","月劳动力需求计划等","ADE","根据使用时间的不同，劳动力需求计划可分为劳动力总需求计划、年度劳动力需求计划和月劳动力需求计划等。",{"id":6,"name":31,"category":32,"favorite":33},"(劳务员)专业管理实务 岗位知识","建筑工程",0]