[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1168003":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1168003,830,2,"多选题","某项目基础底板施工，合同约定工期45天，项目经理部根据业主提供的电子版图纸编制了施工进度（如图），底板施工暂未考虑流水施工。施工进度计划图因业主未按时提供正式图纸，致使工序E在6月6日才开始。基于安全考虑，建设单位要求仍按原合同约定的时间完成底板施工，为此施工单位采取调整劳动力计划，增加劳动力等措施，在15天内完成了2700t钢筋制作（工效为4.5t\u002F人．工作日）。 本工程编制劳动力需求计划时，需要考虑以下参数：（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","工期",true,{"key":16,"text":17,"correct":14},"B","工程量",{"key":19,"text":20,"correct":14},"C","时间定额或产量定额",{"key":22,"text":23,"correct":24},"D","流水节拍",false,{"key":26,"text":27,"correct":14},"E","班次","ABCE","需要考虑的参数又：工期；工程量；时间定额或产量定额；班次",{"id":6,"name":31,"category":32,"favorite":33},"(劳务员)专业管理实务 岗位知识","建筑工程",0]