[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1168002":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1168002,830,2,"多选题","下列各项中，属于劳动力需求计划编制要求的是（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","保持劳动力均衡使用",true,{"key":16,"text":17,"correct":14},"B","准确计算工程量和施工期限",{"key":19,"text":20,"correct":14},"C","根据工程量和定额确定劳动力总量和比例",{"key":22,"text":23,"correct":24},"D","组织施工流水线生产",false,{"key":26,"text":27,"correct":24},"E","设立劳务员管理岗位","ABC","劳动力需求计划的编制要求是：要保持劳动力均衡使用；根据工程的实物量和定额标准分析劳动需用总工日；要准确计算工程量和施工期限。",{"id":6,"name":31,"category":32,"favorite":33},"(劳务员)专业管理实务 岗位知识","建筑工程",0]