[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1168000":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1168000,830,2,"多选题","按定额标定的对象不同，劳动定额又分为单项工序定额、综合定额。下表为砖基础砌体劳动定额（计量单位：m）。 在工作时间的界定中，有效工作时间是从生产效果来看与产品生产直接有关的时间消耗，包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","基本工作时间",true,{"key":16,"text":17,"correct":18},"B","不可避免的中断时间",false,{"key":20,"text":21,"correct":14},"C","辅助工作时间",{"key":23,"text":24,"correct":14},"D","准备与结束工作时间",{"key":26,"text":27,"correct":18},"E","休息时间","ACD","有效工作时间是从生产效果来看与产品生产直接有关的时间消耗，包括基本工作时间、辅助工作时间、准备与结束工作时间。",{"id":6,"name":31,"category":32,"favorite":33},"(劳务员)专业管理实务 岗位知识","建筑工程",0]