[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1167998":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1167998,830,2,"多选题","有效工作时间包括（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","辅助工作时间",true,{"key":16,"text":17,"correct":14},"B","准备与结束工作时间",{"key":19,"text":20,"correct":21},"C","不可避免的中断时间",false,{"key":23,"text":24,"correct":21},"D","偶然的损失时间",{"key":26,"text":27,"correct":14},"E","基本工作时间","ABE","有效工作时间是从生产效果来看与产品生产直接有关的时间消耗，包括基本工作时间、辅助工作时间和准备与结束工作时间。",{"id":6,"name":31,"category":32,"favorite":33},"(劳务员)专业管理实务 岗位知识","建筑工程",0]