[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1167935":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1167935,830,1,"单选题","对于业主指定分包单位的分部、分项工程，由分包单位自行办理设计变更、洽商，但必须经总包项目经理部（ ）审核签字后方可实施。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","总工",true,{"key":16,"text":17,"correct":18},"B","项目经理",false,{"key":20,"text":21,"correct":18},"C","施工员",{"key":23,"text":24,"correct":18},"D","法人代表","对于业主指定分包单位的分部、分项工程，由分包单位自行办理设计变更、洽商，但必须经总包项目经理部总工审核签字后方可实施。",{"id":6,"name":27,"category":28,"favorite":29},"(劳务员)专业管理实务 岗位知识","建筑工程",0]