[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1167914":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1167914,830,1,"单选题","总包负责招标的分包单位在接到总包项目经理部下发的招标图纸或正式图纸后（ ）内必须将所有图纸问题提交总包技术部门。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","6天",false,{"key":16,"text":17,"correct":18},"B","7天",true,{"key":20,"text":21,"correct":14},"C","8天",{"key":23,"text":24,"correct":14},"D","9天","总包负责招标的分包单位在接到总包项目经理部下发的招标图纸或正式图纸后7天内必须将所有图纸问题提交总包技术部门。",{"id":6,"name":27,"category":28,"favorite":29},"(劳务员)专业管理实务 岗位知识","建筑工程",0]