[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1167896":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1167896,830,1,"单选题","劳务分包作业完工并经承包人验收合格之日起（ ）内向承包人提交完工结算申请单和完整的结算资料，承包人在收到完工结算申请单之日（ ）内予以审核确认。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","5天，5天",false,{"key":16,"text":17,"correct":14},"B","7天，7天",{"key":19,"text":20,"correct":14},"C","4天，14天",{"key":22,"text":23,"correct":24},"D","28天，28天",true,"当月完成的工作量应在劳务分包合同专用条款约定的时间内完成结算；劳务分包作业完工并经承包人验收合格之日起28天内向承包人提交完工结算申请单和完整的结算资料，承包人在收到完工结算申请单之日28天内予以审核确认。",{"id":6,"name":27,"category":28,"favorite":29},"(劳务员)专业管理实务 岗位知识","建筑工程",0]