[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1167876":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1167876,830,1,"单选题","属材料物资采购或设备订货的供应单位在结算期，根据订购合同（视为进场计划）的内容和项目经理部物资管理部门材料人员验收（料）小票，报至物资管理部门审核，物资管理部门审核确定签字，再报项目（ ）审核确认签字。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工程部门",false,{"key":16,"text":17,"correct":18},"B","预算部门",true,{"key":20,"text":21,"correct":14},"C","财务部门",{"key":23,"text":24,"correct":14},"D","人事部门","属材料物资采购或设备订货的供应单位在结算期，根据订购合同（视为进场计划）的内容和项目经理部物资管理部门材料人员验收（料）小票，报至物资管理部门审核，物资管理部门审核确定签字，再报项目预算部门审核确认签字。最终，由项目财务部门根据物资部、预算部门的审核意见转账。",{"id":6,"name":27,"category":28,"favorite":29},"(劳务员)专业管理实务 岗位知识","建筑工程",0]