[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1167846":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1167846,830,1,"单选题","总包商资金部门支付工程款项，支付形式为网上转账，（ ）集中办理一次。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","每年",false,{"key":16,"text":17,"correct":14},"B","每季度",{"key":19,"text":20,"correct":21},"C","每月",true,{"key":23,"text":24,"correct":14},"D","每周","分包单位的“工程分包单位合同预、结算单”经总包商主管部门审核签认后，转回项目经理部，项目财务部门填写预结算单及委付单，报总包商资金部门，由总包商资金部门支付款项。支付形式为网上转账，每月集中办理一次。",{"id":6,"name":27,"category":28,"favorite":29},"(劳务员)专业管理实务 岗位知识","建筑工程",0]