[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1167843":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1167843,830,1,"单选题","项目工程管理部门在收到分承包方上报的索赔、签证基础资料（ ）内将审核意见书（包括发生的项目、工程量、影响的程度、工期损失等）发给分包单位，分包单位依据项目工程管理部门的审核意见书编制索赔、签证费用及工期计算书，并上报给项目预算部门审核。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","3日",false,{"key":16,"text":17,"correct":14},"B","5日",{"key":19,"text":20,"correct":14},"C","7日",{"key":22,"text":23,"correct":24},"D","10日",true,"索赔、签证发生后，分包单位将发生的资料（照片或原始记录等）上报项目工程预算部门审核，项目工程管理部门在收到分承包方上报的索赔、签证基础资料10日内将审核意见书（包括发生的项目、工程量、影响的程度、工期损失等）发给分包单位，分包单位依据项目工程管理部门的审核意见书编制索赔、签证费用及工期计算书，并上报给项目预算部门审核。",{"id":6,"name":27,"category":28,"favorite":29},"(劳务员)专业管理实务 岗位知识","建筑工程",0]