[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1167832":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1167832,830,1,"单选题","总承包企业自收到劳务分包承包人依照约定提交的结算资料之日起（ ）内完成审核并书面答复承包人；逾期不答复的，视为发包人同意承包人提交的结算资料。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","28日",true,{"key":16,"text":17,"correct":18},"B","15日",false,{"key":20,"text":21,"correct":18},"C","10日",{"key":23,"text":24,"correct":18},"D","5日","总承包企业自收到劳务分包承包人依照约定提交的结算资料之日起28日内完成审核并书面答复承包人；逾期不答复的，视为发包人同意承包人提交的结算资料。",{"id":6,"name":27,"category":28,"favorite":29},"(劳务员)专业管理实务 岗位知识","建筑工程",0]