[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1167648":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1167648,830,1,"单选题","劳务分包人按约定完成劳务作业，必须由承包人或劳务作业现场内的第三方进行配合时，（ ）应配合劳务分包人工作或确保劳务分包人获得该第三方的配合。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","承包人",true,{"key":16,"text":17,"correct":18},"B","需要配合的第三方",false,{"key":20,"text":21,"correct":18},"C","工程业主",{"key":23,"text":24,"correct":18},"D","合同规定的其他人","根据2014版《建设工程施工劳务分包合同（示范文本）》，合同双方一般义务（作业期限与进度）：劳务分包人按约定完成劳务作业，必须由承包人或劳务作业现场内的第三方进行配合时，承包人应配合劳务分包人工作或确保劳务分包人获得该第三方的配合。",{"id":6,"name":27,"category":28,"favorite":29},"(劳务员)专业管理实务 岗位知识","建筑工程",0]