[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1167647":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1167647,830,1,"单选题","下列（ ）是影响工程施工进度的最关键因素。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","劳务队伍的管理",false,{"key":16,"text":17,"correct":14},"B","进度计划的分解",{"key":19,"text":20,"correct":14},"C","劳务人员的培训",{"key":22,"text":23,"correct":24},"D","劳务队伍人员管理",true,"劳务队伍人员管理是影响工程施工进度的最关键因素。",{"id":6,"name":27,"category":28,"favorite":29},"(劳务员)专业管理实务 岗位知识","建筑工程",0]