[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1167619":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1167619,830,1,"单选题","分包合同价款的支付形式必须采用（ ）形式办理。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","现金",false,{"key":16,"text":17,"correct":18},"B","银行转账",true,{"key":20,"text":21,"correct":14},"C","支票",{"key":23,"text":24,"correct":14},"D","网上支付","分包合同价款的支付必须以银行转账的形式办理。",{"id":6,"name":27,"category":28,"favorite":29},"(劳务员)专业管理实务 岗位知识","建筑工程",0]