[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1167614":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1167614,830,1,"单选题","关于履行劳务分包合同价款的规定，说法错误的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","发包人不得以工程质量纠纷拖欠劳务分包合同价款",false,{"key":16,"text":17,"correct":14},"B","发包人、承包人应当在每月月底前对上月完成劳务作业量级应支付的劳务分包合同价款予以书面确认",{"key":19,"text":20,"correct":21},"C","发包人应当在书面确认后7日内支付已确认的劳务分包合同价款",true,{"key":23,"text":24,"correct":14},"D","承办人应当按照劳务分包合同的约定组织劳务作业人员完成劳务作业内容","发包人应当在书面确认后5日内支付已确认的劳务分包合同价款。",{"id":6,"name":27,"category":28,"favorite":29},"(劳务员)专业管理实务 岗位知识","建筑工程",0]