[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1167610":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1167610,830,1,"单选题","劳务员根据公司所批复的项目进度计划和劳动力使用计划编制进场（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","材料和设备",false,{"key":16,"text":17,"correct":14},"B","人员和设备",{"key":19,"text":20,"correct":21},"C","工种和人数",true,{"key":23,"text":24,"correct":14},"D","材料和工种","劳务员根据公司所批复的项目进度计划和劳动力使用计划编制进场工种、人数一览表。",{"id":6,"name":27,"category":28,"favorite":29},"(劳务员)专业管理实务 岗位知识","建筑工程",0]