[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1167607":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1167607,830,1,"单选题","劳务分包单位负责编制的施工进度计划不包括（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","日计划",false,{"key":16,"text":17,"correct":14},"B","周计划",{"key":19,"text":20,"correct":14},"C","月计划",{"key":22,"text":23,"correct":24},"D","年计划",true,"施工进度计划包括日计划、周计划、月计划。",{"id":6,"name":27,"category":28,"favorite":29},"(劳务员)专业管理实务 岗位知识","建筑工程",0]