[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1167589":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1167589,830,1,"单选题","项目部针对当天（ ）要求等重要事项进行全方位交底，确保施工进度。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","技术措施和经济措施",false,{"key":16,"text":17,"correct":14},"B","劳务人员和过程控制",{"key":19,"text":20,"correct":14},"C","劳务人员和材料进场",{"key":22,"text":23,"correct":24},"D","作业环境、工作内容和进度",true,"劳务队伍的管理是影响工程施工进度的关键因素，劳务员应加强现场劳务队伍的检查监管，项目部制订相应激励和奖罚措施，提高队伍管理水平，为保证施工进度计划的顺利完成创造条件。项目部针对当天作业环境、工作内容、工程进度要求等重要事项进行全方位交底，促进劳务队伍细化管理、有效管控，保证工程施工进度。",{"id":6,"name":27,"category":28,"favorite":29},"(劳务员)专业管理实务 岗位知识","建筑工程",0]