[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1167584":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1167584,830,1,"单选题","因承包人原因未按计划开始工作日期开始工作的，承包人应按实际开始工作日期顺延作业期限，确保实际作业期限（ ）合同约定的作业总日历天数。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","不高于",false,{"key":16,"text":17,"correct":18},"B","不低于",true,{"key":20,"text":21,"correct":14},"C","等同于",{"key":23,"text":24,"correct":14},"D","不延长","根据2014版《建设工程施工劳务分包合同（示范文本）》，合同双方一般义务（作业期限与进度）：因承包人原因未按计划开始工作日期开始工作的，承包人应按实际开始工作日期顺延作业期限，确保实际作业期限不低于合同约定的作业总日历天数。",{"id":6,"name":27,"category":28,"favorite":29},"(劳务员)专业管理实务 岗位知识","建筑工程",0]