[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1167514":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1167514,830,1,"单选题","某队有生产工人100人，7月份病事假72工日，开会学习40工日，公休假日8天，加班450工日，出差、联系材料20工日，其中1人协助炊事班，2人守卫，其与工人没有执行定额的620工日，全月共完成定额工日2025工日。则7月份执行定额面为（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","65.46%",false,{"key":16,"text":17,"correct":18},"B","75.68%",true,{"key":20,"text":21,"correct":14},"C","78.46%",{"key":23,"text":24,"correct":14},"D","79.44%","全部作业工日=[（月平均人数—非生产人数）×（日历天数—公休天数）]—缺勤工日—非生产工日+加班工日=[（100—1—2）×（31—8）]—72—40—20+450=2549工日。执行定额工日=全部作业工日—未执行定额工日=2549—620=1929工日。执行定额面=1929÷2549×100%=75.68%。",{"id":6,"name":27,"category":28,"favorite":29},"(劳务员)专业管理实务 岗位知识","建筑工程",0]