[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1167513":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1167513,830,1,"单选题","在施工准备阶段，（ ）首先根据投标文件中的施工组织设计编制劳务用工需求量计划。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","总承包单位公司",false,{"key":16,"text":17,"correct":14},"B","施工劳务企业",{"key":19,"text":20,"correct":21},"C","项目部",true,{"key":23,"text":24,"correct":14},"D","劳务队伍","在施工准备阶段，项目部根据投标文件中的施工组织设计编制劳务用工需求量计划。根据开、竣工时间和具体施工部位的工程量，确定该项目需要的各工种在每个月的施工人数、进退场时间。",{"id":6,"name":27,"category":28,"favorite":29},"(劳务员)专业管理实务 岗位知识","建筑工程",0]