[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1167504":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1167504,830,1,"单选题","某项目基础底板施工，合同约定工期45天，项目经理部根据业主提供的电子版图纸编制了施工进度（如图），底板施工暂未考虑流水施工。施工进度计划图因业主未按时提供正式图纸，致使工序E在6月6日才开始。基于安全考虑，建设单位要求仍按原合同约定的时间完成底板施工，为此施工单位采取调整劳动力计划，增加劳动力等措施，在15天内完成了2700t钢筋制作（工效为4.5t\u002F人．工作日）。 劳动力总需求计划的编制方法不包括（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","经验比较法",false,{"key":16,"text":17,"correct":14},"B","分项综合系数法",{"key":19,"text":20,"correct":14},"C","概算定额法",{"key":22,"text":23,"correct":24},"D","技术测定法",true,"3.1.2.2劳动力总需求计划的编制方法：1.经验比较法；2.分项综合系数法；3.概算定额法；4.公式法",{"id":6,"name":27,"category":28,"favorite":29},"(劳务员)专业管理实务 岗位知识","建筑工程",0]