[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1167503":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1167503,830,1,"单选题","某工程承包作业5000平方米，计划每平方米单位用工5个工日，每个工日单价40元，计划工期为306天，计划劳动生产率指数120%。则计划平均人数为（ ）人。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","72",false,{"key":16,"text":17,"correct":18},"B","82",true,{"key":20,"text":21,"correct":14},"C","91",{"key":23,"text":24,"correct":14},"D","85","计划平均人数=计划用工总工日\u002F计划工期天数=5000*5\u002F306=82人。",{"id":6,"name":27,"category":28,"favorite":29},"(劳务员)专业管理实务 岗位知识","建筑工程",0]