[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1167502":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1167502,830,1,"单选题","劳动力总量需求计划的编制程序不包括（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","确定劳动效率",false,{"key":16,"text":17,"correct":14},"B","确定劳动力投入量",{"key":19,"text":20,"correct":21},"C","确定劳动总产量",true,{"key":23,"text":24,"correct":14},"D","编制劳动力需求计划","劳动力总量需求计划的编制程序包括：确定劳动效率、确定劳动力投入量、编制劳动力需求计划。",{"id":6,"name":27,"category":28,"favorite":29},"(劳务员)专业管理实务 岗位知识","建筑工程",0]