[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1167494":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1167494,830,1,"单选题","当绘制企业各项目劳动力负荷曲线数据不足时，可以采用（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","标准（典型）横道法",false,{"key":16,"text":17,"correct":14},"B","标准（典型）直方图法",{"key":19,"text":20,"correct":21},"C","标准（典型）曲线法",true,{"key":23,"text":24,"correct":14},"D","劳动力动员直方图法","当绘制企业各项目劳动力负荷曲线数据不足时，可以采用标准（典型）曲线法，即套用已有的同类项目标准（典型）劳动力负荷曲线，根据现有项目情况加以修正。",{"id":6,"name":27,"category":28,"favorite":29},"(劳务员)专业管理实务 岗位知识","建筑工程",0]