[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1167493":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1167493,830,1,"单选题","某项目基础底板施工，合同约定工期45天，项目经理部根据业主提供的电子版图纸编制了施工进度（如图），底板施工暂未考虑流水施工。施工进度计划图因业主未按时提供正式图纸，致使工序E在6月6日才开始。基于安全考虑，建设单位要求仍按原合同约定的时间完成底板施工，为此施工单位采取调整劳动力计划，增加劳动力等措施，在15天内完成了2700t钢筋制作（工效为4.5t\u002F人．工作日）。 劳动力总需求计划的编制程序中，第一步是：（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","确定劳动力投人量",false,{"key":16,"text":17,"correct":18},"B","确定劳动效率",true,{"key":20,"text":21,"correct":14},"C","计算流水步距",{"key":23,"text":24,"correct":14},"D","计算流水节拍","3.1、2.1劳动力总需求计划的编制程序：1.确定劳动效率；2.确定劳动力投入量；3.劳动力需求计划的编制",{"id":6,"name":27,"category":28,"favorite":29},"(劳务员)专业管理实务 岗位知识","建筑工程",0]