[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1167490":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1167490,830,1,"单选题","某工程承包作业5000㎡，计划每平方米单位用工5个工日，每个工日单价40元，计划工期为306天，计划劳动生产率指数为120％。计划用工为（ ）工日。（保留整数）",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","82",false,{"key":16,"text":17,"correct":14},"B","100",{"key":19,"text":20,"correct":14},"C","200000",{"key":22,"text":23,"correct":24},"D","20833",true,"计划实际用工的计算：计划实际用工=计划用工总工日\u002F计划劳动生产率指数计划实际用工=5000*5\u002F120%=20833",{"id":6,"name":27,"category":28,"favorite":29},"(劳务员)专业管理实务 岗位知识","建筑工程",0]