[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1167477":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1167477,830,1,"单选题","关于劳务管理计划的目标的确定，说法正确的是：（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","劳务管理的目标只确定总目标",false,{"key":16,"text":17,"correct":14},"B","劳务管理的目标不应将总目标和分目标分别设置",{"key":19,"text":20,"correct":21},"C","劳务管理的目标应分为总目标和分目标",true,{"key":23,"text":24,"correct":14},"D","劳务管理的目标只设置分目标","项目劳务管理制度不能完全照搬公司的劳务管理制度，而是要依据公司的劳务管理制度结合本项目的具体情况。劳务管理的目标应分为总目标和分目标。",{"id":6,"name":27,"category":28,"favorite":29},"(劳务员)专业管理实务 岗位知识","建筑工程",0]