[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1167466":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1167466,830,1,"单选题","劳动力需求量计划还应包括对现场其他人员的使用计划，现场其他人员是指（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","总包单位现场管理人员",false,{"key":16,"text":17,"correct":14},"B","专业分包单位现场管理人员",{"key":19,"text":20,"correct":14},"C","施工劳务单位现场管理人员",{"key":22,"text":23,"correct":24},"D","工地警卫、勤杂人员",true,"劳动力需求量计划还应包括对现场其他人员的使用计划，如为劳动力服务的人员（如厨师、司机等）、工地警卫、勤杂人员、工地管理人员等，可根据劳动力投人量计划按比例计算，或根据现场实际需要安排。",{"id":6,"name":27,"category":28,"favorite":29},"(劳务员)专业管理实务 岗位知识","建筑工程",0]