[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1167465":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1167465,830,1,"单选题","劳动力负荷曲线是（ ）的包络曲线。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","劳动力动员排列图",false,{"key":16,"text":17,"correct":14},"B","劳动力动员横道图",{"key":19,"text":20,"correct":21},"C","劳动力动员直方图",true,{"key":23,"text":24,"correct":14},"D","劳动力动员网络图","劳动力负荷曲线就是劳动力动员直方图的包络曲线，曲线有限点的坐标值的表格形成就是劳动力动员计划表。",{"id":6,"name":27,"category":28,"favorite":29},"(劳务员)专业管理实务 岗位知识","建筑工程",0]