[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1167448":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1167448,830,1,"单选题","劳动定额按其表现形式不同，分为（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","时间定额和产量定额",true,{"key":16,"text":17,"correct":18},"B","时间定额和预算定额",false,{"key":20,"text":21,"correct":18},"C","施工定额和产量定额",{"key":23,"text":24,"correct":18},"D","施工定额和预算定额","2、1.1.2劳动定额的表达形式劳动定额按其表现形式不同，分为时间定额和产量定额。",{"id":6,"name":27,"category":28,"favorite":29},"(劳务员)专业管理实务 岗位知识","建筑工程",0]