[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1167446":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1167446,830,1,"单选题","按定额标定的对象不同，劳动定额又分为单项工序定额、综合定额。下表为砖基础砌体劳动定额（计量单位：m）。 根据上表，厚度1砖的综合时间定额为（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","427工日",false,{"key":16,"text":17,"correct":14},"B","0.86工日",{"key":19,"text":20,"correct":14},"C","0.336工日",{"key":22,"text":23,"correct":24},"D","89工日",true,"根据上表可知：厚度1砖的综合时间定额为89工日",{"id":6,"name":27,"category":28,"favorite":29},"(劳务员)专业管理实务 岗位知识","建筑工程",0]