[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1167442":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1167442,830,1,"单选题","工人在工作班内消耗的工作时间，按其消耗的性质，可以分为两大类：（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","有效工作时间和停工时间",false,{"key":16,"text":17,"correct":18},"B","必须消耗的时间和损失时间",true,{"key":20,"text":21,"correct":14},"C","必须消耗的时间和休息时间",{"key":23,"text":24,"correct":14},"D","必须消耗的时间和停工时间","根据2.2工作时间的界定条例：工人在工作班内消耗的工作时间，按其消耗的性质，可以分为两大类；必须消耗的时间（定额时间）和损失时间（非定额时间）。",{"id":6,"name":27,"category":28,"favorite":29},"(劳务员)专业管理实务 岗位知识","建筑工程",0]