[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1167440":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1167440,830,1,"单选题","工人在工作班内消耗的工作时间，按其消耗的性质可以分为（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","定额时间和休息时间",false,{"key":16,"text":17,"correct":14},"B","有效时间和损失时间",{"key":19,"text":20,"correct":14},"C","必须消耗的时间和中断时间",{"key":22,"text":23,"correct":24},"D","必须消耗的时间和损失时间",true,"工人在工作班内消耗的工作时间，按其消耗的性质可以分为必须消耗的时间和损失时间。",{"id":6,"name":27,"category":28,"favorite":29},"(劳务员)专业管理实务 岗位知识","建筑工程",0]