[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1167435":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1167435,830,1,"单选题","用经验估工法确定某一个施工过程单位合格产品工时消耗，通过座谈讨论估计出了三种不同的的工时消耗，分别为0.45、0.6、0.7，计算器定额时间为（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","0.51",false,{"key":16,"text":17,"correct":18},"B","0.59",true,{"key":20,"text":21,"correct":14},"C","0.63",{"key":23,"text":24,"correct":14},"D","0.67","定额时间t=（0.45+4*0.6+0.7）\u002F6=0.59。",{"id":6,"name":27,"category":28,"favorite":29},"(劳务员)专业管理实务 岗位知识","建筑工程",0]