[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1167202":3},{"question":4,"library":19},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":13,"analysis":9},1167202,829,3,"判断题","按照工程重要程度，单位工程开工前，应由企业或项目技术负责人向承担施工的负责人或分包人进行全面技术交底。",[11,15],{"key":12,"text":13,"correct":14},"A","正确",true,{"key":16,"text":17,"correct":18},"B","错误",false,{"id":6,"name":20,"category":21,"favorite":22},"(劳务员)基础知识","建筑工程",0]