[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1167195":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":17,"analysis":19},1167195,829,3,"判断题","建设工程项目质量政府监督的内容主要包括：建设工程的质量监督评估、开工前的质量监督、在施工期间的质量监督、竣工阶段的质量监督。",[11,15],{"key":12,"text":13,"correct":14},"A","正确",false,{"key":16,"text":17,"correct":18},"B","错误",true,"建设工程项目质量政府监督的内容包括：受理质量监督申请，开工前的质量监督，施工期间的质量监督，竣工阶段的质量监督。",{"id":6,"name":21,"category":22,"favorite":23},"(劳务员)基础知识","建筑工程",0]