[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1167180":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":17,"analysis":19},1167180,829,3,"判断题","在工程开工前，由总包单位技术部门编制施工项目管理实施规划，对施工项目管理从开工到交工验收进行全面的指导性规划。",[11,15],{"key":12,"text":13,"correct":14},"A","正确",false,{"key":16,"text":17,"correct":18},"B","错误",true,"工程开工前，项目部不曾建立，应由企业指定拟派往的项目经理组织拟派的项目技术负责人等，编制该工程的施工组织设计（这不同于投标用的，应该更有针对性、更能落实的），以便从开工到竣工验收进行全面的指导和达到的目标。",{"id":6,"name":21,"category":22,"favorite":23},"(劳务员)基础知识","建筑工程",0]