[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1166940":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1166940,829,2,"多选题","施工项目进度的比较分析常用的方法有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","网络图记录比较法",false,{"key":16,"text":17,"correct":18},"B","横道图记录比较法",true,{"key":20,"text":21,"correct":18},"C","前锋线比较法",{"key":23,"text":24,"correct":18},"D","香蕉形曲线比较法",{"key":26,"text":27,"correct":18},"E","s形曲线比较法","BCDE","横道图记录比较法、s形曲线比较法、前锋线比较法、香蕉形曲线比较法是施工项目进度的比较分析。",{"id":6,"name":31,"category":32,"favorite":33},"(劳务员)基础知识","建筑工程",0]