[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1166931":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1166931,829,2,"多选题","施工准备阶段的主要工作包括（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","由项目经理部编制开工报告",true,{"key":16,"text":17,"correct":14},"B","项目经理部抓紧做好各项施工准备",{"key":19,"text":20,"correct":14},"C","企业管理层委派项目经理",{"key":22,"text":23,"correct":24},"D","项目经理组织招聘劳务班组",false,{"key":26,"text":27,"correct":24},"E","项目经理组织购买大宗材料","ABC","施工准备阶段的目标是是工程具备开工和连续施工的基本条件。该阶段的主要工作包括：①企业管理层委派项目经理，有项目经理组建项目经理部，根据工程项目管理需要建立健全管理机构，配备管理人员；②企业管理层与项目经理协商签订《施工项目管理目标责任书》，明确项目经理应承担的责任目标及各项管理任务；③由项目经理组织编制《施工项目管理实施规划》；④项目经理部抓紧做好施工各项准备工作，达到开工要求；⑤由项目经理部编写开工报告，上报，获得批准后开工。",{"id":6,"name":31,"category":32,"favorite":33},"(劳务员)基础知识","建筑工程",0]