[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1166929":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1166929,829,2,"多选题","施工项目进度计划系统包括施工项目（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","项目总进度计划",true,{"key":16,"text":17,"correct":14},"B","单位工程进度计划",{"key":19,"text":20,"correct":14},"C","分部分项工程进度计划",{"key":22,"text":23,"correct":24},"D","材料进场计划",false,{"key":26,"text":27,"correct":14},"E","年度月度进度计划","ABCE","施工项目进度计划系统包括施工项目的项目总进度计划、单位工程进度计划、分部分项工程进度计划、年度月度进度计划",{"id":6,"name":31,"category":32,"favorite":33},"(劳务员)基础知识","建筑工程",0]