[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1166925":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1166925,829,2,"多选题","施工项目管理的目标应符合合同的要求，其主要内容包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","施工的质量目标",true,{"key":16,"text":17,"correct":18},"B","施工的利润目标",false,{"key":20,"text":21,"correct":14},"C","施工的进度目标",{"key":23,"text":24,"correct":14},"D","施工的安全管理目标",{"key":26,"text":27,"correct":14},"E","文明施工和环境保护目标","ACDE","施工项目管理的目标应符合合同的要求，其主要内容包括施工的质量目标、施工的进度目标、施工的安全管理目标、文明施工和环境保护目标等",{"id":6,"name":31,"category":32,"favorite":33},"(劳务员)基础知识","建筑工程",0]