[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1166920":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1166920,829,2,"多选题","下列各项中，不属于施工项目管理的内容的是（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","建立施工项目管理组织",false,{"key":16,"text":17,"correct":18},"B","编制《施工项目管理目标责任书》",true,{"key":20,"text":21,"correct":14},"C","施工项目的生产要素管理",{"key":23,"text":24,"correct":18},"D","施工项目的施工情况的评估",{"key":26,"text":27,"correct":14},"E","施工项目的信息管理","BD","施工项目管理包括以下八方面内容：建立施工项目管理组织、编制施工项目管理规划、施工项目的目标控制、施工项目的生产要素管理、施工项目的合同管理、施工项目的信息管理、施工现场的管理、组织协调等。",{"id":6,"name":31,"category":32,"favorite":33},"(劳务员)基础知识","建筑工程",0]