[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1166909":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1166909,829,2,"多选题","下列关于钢结构安装施工要点的说法中，错误的是（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","起吊事先将钢构件吊离地面30Cm左右，使钢构件中心对准安装位置中心",true,{"key":16,"text":17,"correct":14},"B","高强度螺栓上、下接触面处加有1\u002F15以上斜度时应采用垫圈垫平",{"key":19,"text":20,"correct":21},"C","施焊前，焊工应检查焊接件的接头质量和焊接区域的坡口、间隙、钝边等的处理情况",false,{"key":23,"text":24,"correct":21},"D","厚度大于12～20mm的板材，单面焊后，背面清根，再进行焊接",{"key":26,"text":27,"correct":14},"E","焊道两端加引弧板和熄弧板，引弧和熄弧焊缝长度应大于或等于150mm","ABE","起吊事先将钢构件吊离地面50Cm左右，使钢构件中心对准安装位置中心，然后徐徐升钩，将钢构件吊至需连接位置即刹车对准预留螺栓孔，并将螺栓穿入孔内，初拧作临近固定，同时进行垂直度校正和最后固定，经校正后，并终拧螺栓作最后固定。高强度螺栓上、下接触面处加有1\u002F20以上斜度时应采用垫圈垫平。施焊前，焊工应检查焊接件的接头质量和焊接区域的坡口、间隙、钝边等的处理情况。厚度大于12～20mm的板材，单面焊后，背面清根，再进行焊接。焊道两端加引弧板和熄弧板，引弧和熄弧焊缝长度应大于或等于80mm。",{"id":6,"name":31,"category":32,"favorite":33},"(劳务员)基础知识","建筑工程",0]