[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1166908":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1166908,829,2,"多选题","下列关于柱钢筋和板钢筋绑扎的施工工艺的规定中正确的是（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","柱钢筋绑扎中箍筋的接头应交错布置在四角纵向钢筋上，箍筋转角与纵向钢筋交叉点均应扎牢",true,{"key":16,"text":17,"correct":18},"B","板钢筋绑扎中板、次梁与主梁交叉处，板的钢筋在上，次梁的钢筋居中。主梁的钢筋一直在下侧",false,{"key":20,"text":21,"correct":14},"C","板钢筋绑扎的施工工艺流程为：清理垫层、划线→摆放下层钢筋，并固定绑扎→摆放钢筋撑脚（双层钢筋时）→安装管线→绑扎上层钢筋",{"key":23,"text":24,"correct":14},"D","对于双向受力板，应先铺设平行于短边方向的受力钢筋，后铺设平行于长边方向的受力钢筋",{"key":26,"text":27,"correct":18},"E","板上部的负筋、主筋与分布钢筋的交叉点应相隔交错扎牢，并垫上保护层垫块","ACD","柱钢筋绑扎中箍筋的接头应交错布置在四角纵向钢筋上，箍筋转角与纵向钢筋交叉点均应扎牢。",{"id":6,"name":31,"category":32,"favorite":33},"(劳务员)基础知识","建筑工程",0]