[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1166813":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1166813,829,1,"单选题","建设工程项目的整个实施过程较长，在这漫长的过程中由于社会、政治、经济、市场的变化以及（ ）有可能发生的不可预知事件，会直接或间接影响工程项目的正常实施，造成承包人利润的减少甚至亏损。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","设计变更",false,{"key":16,"text":17,"correct":14},"B","政策变化",{"key":19,"text":20,"correct":21},"C","工程实施过程中",true,{"key":23,"text":24,"correct":14},"D","不可抗力","建设工程项目的整个实施过程较长，在这漫长的过程中由于社会、政治、经济、市场的变化以及工程实施过程中有可能发生的不可预知事件，会直接或间接影响工程项目的正常实施，造成承包人利润的减少甚至亏损。",{"id":6,"name":27,"category":28,"favorite":29},"(劳务员)基础知识","建筑工程",0]