[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1166795":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1166795,829,1,"单选题","承包人提供的材料在进场时应由（ ）负责验收。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","承包人自己",false,{"key":16,"text":17,"correct":18},"B","劳务分包人",true,{"key":20,"text":21,"correct":14},"C","材料员",{"key":23,"text":24,"correct":14},"D","双方一起","承包人提供的材料在进场时应由劳务分包人负责验收，如材料的品种、规格、型号、质量、数量不符合要求，劳务分包人应在验收时提出，由此增加的费用和（或）延误的期限均由承包人承担。",{"id":6,"name":27,"category":28,"favorite":29},"(劳务员)基础知识","建筑工程",0]